Key Points

  • Strata council review typically runs two to four weeks, because councils decide alteration requests at scheduled meetings rather than on demand

  • Cosmetic work is generally exempt. Anything touching plumbing, electrical, structure, flooring sound ratings, or common property generally is not

  • The bylaws registered against your building govern, not a generic template, so read them before designing the scope

  • Most rejections are administrative: incomplete drawings, missing contractor licensing and insurance, or scope submitted in pieces

How do I get strata approval for a renovation in Vancouver? Read the bylaws registered for your building, submit a written alteration request to the strata council with drawings and your contractor's licensing and insurance documents, wait through a council review that typically runs two to four weeks, accept the conditions attached to the approval, then book elevator and noise windows before work starts. Nothing gets demolished until the approval is in writing.

That is the sequence. The detail below covers what council is actually looking at, what does not need approval at all, and the reasons requests come back rejected.


What Strata Approval Is and Why It Exists

In a strata building you own the airspace inside your unit. You do not own the pipes in the walls, the concrete slab, the building envelope, or the corridors. Those are common property, held collectively by every owner in the building. The moment a renovation touches them, it stops being your decision alone.

The Strata Property Act and the bylaws registered against your building set out how that works. Under the Act's standard bylaws, an owner must get written approval from the strata corporation before altering common property, and before certain alterations to a strata lot itself. Most strata corporations have filed their own bylaws in the Land Title Office that replace or expand on the standard set, so the rules that bind you are the ones registered for your building, not a generic template.

Three interests sit behind the requirement.

Building systems. Drainage stacks, risers, and electrical distribution are shared. A change made in one unit can affect units above and below it for the life of the building.

Insurance. The strata corporation carries a policy over the whole building. Unapproved work that causes damage can put a claim in dispute, and the cost can be assigned back to the owner who did the work.

Other owners. Noise, elevator monopolies, and blocked loading bays affect everyone. Approval conditions are how a council keeps one renovation from making the building unlivable for a month.

Some changes go beyond what a council can approve on its own. Where a project would significantly change the use or appearance of common property, the decision can require a three-quarters vote of the owners at a general meeting rather than a council sign-off. That is a different timeline and worth identifying early.

Limited common property catches people out

Balconies, patios, parking stalls, and storage lockers are usually limited common property. You have exclusive use of them, which owners routinely mistake for ownership. They remain common property, so enclosing a balcony, changing its flooring, or installing anything fixed to it needs the same written approval as work in a corridor. Exclusive use is not the same as a free hand.

The same logic applies to anything inside your walls that serves more than your unit. A drainage stack passing through your bathroom serves the whole column of units above you. Rerouting around it is your business. Cutting into it is not.


When Approval Is Required, and When It Is Not

The dividing line is whether the work stays inside your own finishes or reaches into shared systems and structure. Cosmetic work generally does not need approval. Anything touching plumbing, electrical, structure, or common property generally does.

Typically exemptTypically requires approval
Painting and wallpaperMoving or adding plumbing rough-in
Replacing cabinet doors and hardwareRelocating or adding electrical circuits
Swapping light fixtures on existing circuitsAny change to walls, slab, or structure
Replacing a faucet or toilet at the existing rough-inFlooring changes, because of sound transmission
Window coverings and blindsWork touching the building envelope, windows, or balconies
Furniture and freestanding shelvingBathroom and kitchen renovations of any real scope

Two cautions on that table. Flooring surprises people: replacing carpet with hardwood or tile changes how sound travels to the unit below, and most Vancouver strata bylaws set a minimum sound rating and require the specification to be submitted for approval. And treat the table as a guide, not an answer. Your registered bylaws govern, and some buildings require an application for work that others wave through.

A bathroom renovation or a kitchen renovation in a strata unit will need approval in almost every case, because both move water and add circuits.


The Strata Approval Process, Step by Step

Step 1: Review your strata bylaws

Request the current registered bylaws and rules from the property manager, along with any alteration policy the council has adopted. Read what your building defines as an alteration, what documents the request must include, and whether an alteration agreement is required. This step costs nothing and prevents most rejections.

Step 2: Submit the alteration request

Submit a written request to the council through the property manager. A complete package includes a scope description, drawings or a marked-up floor plan showing existing and proposed conditions, the trades involved, your contractor's business licence, WorkSafeBC registration, proof of liability insurance, and the proposed schedule. Where the strata requires an alteration agreement, that document assigns future responsibility for the altered element to you and to subsequent owners of your unit.

Step 3: Council review

Councils review alteration requests at their scheduled meetings, which is why the process takes time rather than because anyone is being slow. Two to four weeks is the normal window. Buildings whose councils meet monthly can run longer, and a request that arrives just after a meeting waits for the next one. Incomplete packages restart the clock.

Step 4: Approval and conditions

Approval usually arrives with conditions attached: permitted work hours, elevator booking requirements, protection of corridors and lobbies, a damage deposit, insurance certificates naming the strata corporation, and a completion deadline. Read the conditions before accepting. They are binding and they shape the construction schedule.

Step 5: Contractor coordination

Book the elevator and loading bay for the delivery and demolition days. Confirm the trades know the permitted hours. Where the scope requires a City of Vancouver building permit for plumbing, electrical, or structural work, that application runs after strata approval is granted, because the City will expect the strata to have signed off first. Build both review periods into the schedule rather than assuming they overlap.

Step 6: Completion sign-off

Notify the council when the work is finished. Many buildings inspect the corridors and elevator for damage before releasing the deposit. Keep the approval letter, the alteration agreement, and the closed permit together. Those documents get requested at resale, and a buyer's lawyer will ask about work that has no paper trail.


Why Requests Get Rejected

Most rejections are administrative, not substantive. The council is not refusing the renovation. It is refusing the paperwork.

ReasonWhat fixes it
Incomplete documentationSubmit drawings showing existing and proposed conditions, not a written description alone
Missing contractor credentialsInclude the business licence, WorkSafeBC registration, and liability insurance certificate in the first submission
Scope creep beyond the submitted requestApply for the full scope up front, including work you are still deciding on
Work hours conflicting with bylawsPropose a schedule inside the building's permitted hours instead of asking for an exception
No sound rating for flooringProvide the manufacturer's rating and the underlayment specification with the request
Ignoring the alteration agreementSign and return it with the package rather than treating it as optional

Scope creep is the expensive one. An approval covers what was submitted. Deciding mid-project to move a wall that was not in the request means going back to council and stopping work while you wait.

What happens if you skip approval

A strata corporation that finds unapproved work can order it removed and the unit restored at the owner's cost. It can fine under its bylaws, and it can refuse elevator and building access, which halts the job regardless of what the contractor has scheduled. Where unapproved work later causes damage, the owner can be left carrying a repair the building's policy would otherwise have covered.

The problem outlasts the renovation. Unapproved alterations surface at resale, when a buyer's lawyer orders the Form B information certificate and the strata minutes. Minutes recording an unresolved alteration complaint will be read by every prospective buyer, and an alteration agreement that was never signed leaves the liability question open for whoever owns the unit next.


How a Licensed Contractor Speeds Up Approval

Councils approve faster when the submission answers their questions before they ask. A contractor who works in strata buildings regularly has the documentation ready as a matter of course: a current business licence, active WorkSafeBC registration, liability insurance at the coverage level the building requires, and a certificate naming the strata corporation as an additional insured.

That documentation does more than satisfy a checklist. WorkSafeBC registration matters to the council because an unregistered contractor's injured worker can become a liability question for the building. Proof of insurance matters because the strata's own policy should never be the first line of defence for damage caused by an owner's renovation. A submission that closes both of those questions in the first package removes the two most common reasons a council defers a decision to its next meeting.

Drawings matter as much. A marked-up floor plan showing what is there now and what is proposed lets a council review the request in one sitting. A paragraph of description invites questions, and questions cost a meeting cycle.

For the full scope of what a strata renovation involves, including sound ratings, wet-wall constraints, and elevator logistics, see condo renovation Vancouver.

Strata Approval Questions

How long does strata renovation approval take in Vancouver?

Two to four weeks is the normal range. Strata councils decide alteration requests at scheduled meetings rather than on demand, so timing depends on the meeting cycle. A request submitted just after a meeting waits for the next one, and an incomplete package restarts the review.

Do I need strata approval to paint or replace flooring?

Painting is generally exempt. Flooring generally is not. Replacing carpet with hardwood or tile changes how sound travels to the unit below, and most Vancouver strata bylaws set a minimum sound rating and require the flooring and underlayment specification to be submitted for approval.

Can a strata council refuse my renovation request?

A council can refuse a request, but it must act in good faith rather than arbitrarily. In practice most refusals are administrative: missing drawings, absent contractor licensing or insurance, or a scope that changed after submission. Resubmitting a complete package resolves the majority of them.

Do I need strata approval for a balcony renovation?

Yes, in almost every case. Balconies and patios are usually limited common property, meaning you have exclusive use but not ownership. Enclosing a balcony, changing its flooring, or fixing anything to it requires the same written approval as work on any other common property.

What happens if I renovate without strata approval?

The strata corporation can order the work removed and the unit restored at your cost, fine under its bylaws, and withhold elevator and building access. Unapproved alterations also surface at resale through the Form B information certificate and the strata minutes, leaving the liability question open for the next owner.


Get Started

Strata projects start with the alteration request, not demolition. Every quote includes the drawings, licensing, and insurance documentation your council needs to decide at one meeting instead of three.